Location: Charlton

  1. Location: Charlton, immediately north of TGP mainline on west side of Route 169 
  2. Company: Tennessee Gas, Kinder Morgan 
  3. Agency: FERC, EFSB 
  4. Docket Numbers: blanket auth, EFS 18-04/DPU 18-96, approved 2021
  5. Description
    1. Pipeline interconnection and meter station = shorter duration than Facility construction, occur concurrently with NG liquefaction, storage, and truck loading facility by NEC
    2. Grading, earthwork, installation of concrete foundations, interconnection piping, electrical/instrumentation equipment 
  6. Links
    1. https://northeastenergycenter.com/projectoverview/ 
    2. Notice of Second Public Comment Hearing (2019) 
    3. EFSB Approval Summary (2021, page 73) 
  7. Petition before EFSB 2019